A. Review Process I. If a complete application has not been filed for a building permit or equivalent construction permit within two years on a project for which a land use permit has been granted under Review Process I, and an extension has not been granted:

1. The land use permit shall be deemed to be terminated, except where a time limit on the land use permit is otherwise established by federal or state law, city ordinance, or an executed development agreement.

2. If the permittee requests an extension in writing not later than two years from the land use permit date, the planning director may grant a six-month extension.

B. Review Process II and III. If a complete application has not been filed for a building permit or equivalent construction permit within three years on a project for which a land use permit has been granted under Review Process II or III, and an extension has not been granted:

1. The land use permit shall be deemed to be terminated, except where a time limit on the land use permit is otherwise established by federal or state law, city ordinance, or an executed development agreement.

2. If the permittee requests an extension in writing not later than three years from the land use permit date, the planning director may grant a six-month extension.

3. For any reapplication, the city may use the existing SEPA determination or may require new or additional environmental documents as provided by WAC 197-11-600. (Ord. 3774-20 § 3 (Exh. 2), 2020.)